Feasibility of running a 24*7 Endurance Test for SAP ECC Load runner GUI scripts in PC ALM

Please let me know what are the challenges are observed when we run SAP GUI load runner scripts in PC ALM for 24*7 days. Is it possible to run such a long test?

Thanks,

Karun Chelikani

Parents
  • Hello, 

    Is important to consider following estatements: 

    1. Bandwith.

    2. Free space in disk in LoadGenerator machine.

    3. Make sure that there is no firewall that may block files transfer during test execution.

    4. Make sure to disable results collection before start the test. This will prevent the overload.

    Kind regards,

Reply