Upgrading from PC 11 to 12

Hi,

 

Given the impending end of support for PC 11 I need to upgrade. 
I have only previously upgraded QC. How long do QC projects take to upgrade by comparisson? In QC it can take a long time if projects have a lot of information and tests that need updating. 
Our PC projects are smaller than QC ones and have less tests but may have many many results.

Are there any pointers on how long PC upgrades take to help us plan project downtime?

 

Thanks

Andy

  • Hi,

     

    It is hard to say exactly how much time it takes to upgrade a project, it depends on the databse size, reponsitory size, DB server performance, reponsitory location, DB server location....

     

    But upgrading from ALM 11 to ALM 12 speed was improved a lot.