Rhythm Tracking View Prediction Algorithms

Can anyone explain the when the following terms mean in the Tracking View and how the various numbers are calculated. I have looked in the online help and the answers are quite vague. I really would appreciate some detailed explanation of the calculations used. Thanks.

Operating Capacity

Operating Velocity

Projected Completion Date.

Parents
  • The Operating Velocity displays as N/A when the numbers used for the calculation are not valid. Examples are, when there not any stories assigned to the release, or when all assigned stories have 0 point estimates. It most commonly happens early in the release definition process.

    We do appreciate that some teams may not use point estimates for planning (more often true when using a Kanban methodology). We are in the process of defining an option to present tracking metrics based on story counts, not points. This will provide an alternative should your team work in this manner.
Reply
  • The Operating Velocity displays as N/A when the numbers used for the calculation are not valid. Examples are, when there not any stories assigned to the release, or when all assigned stories have 0 point estimates. It most commonly happens early in the release definition process.

    We do appreciate that some teams may not use point estimates for planning (more often true when using a Kanban methodology). We are in the process of defining an option to present tracking metrics based on story counts, not points. This will provide an alternative should your team work in this manner.