How can I schedule the same test to be executed multiple times within SilkCentral Test Manager?

0 Likes

Problem:

How can I schedule the same test to be executed multiple times within SilkCentral Test Manager?

Resolution:

QUESTION
----------------------------------

How can I schedule the same test to be executed multiple times within SilkCentral Test Manager?

ANSWER
----------------------------------

  1. Go to Test Manager / Overview / Project / .

  2. Navigate to the Test Definition that you want to schedule and select the Schedule Test Definition:

  3. Input the date and time that you want the first execution to begin.

  4. Specify the time interval between each execution

  5. Choose how many times that you want the test to be executed

  6. Then select save.