What does the "Time Left" field in the execution window represent?

0 Likes

Problem:

What does the "Time Left" field in the execution window represent?

Resolution:

ANSWER
----------------------------------
The "Time Left" indicator is used to display how much longer is left before the test definition will be completed. This time is measured on the first execution of the test definition and then subsequent executions will use this time as a baseline to determine their approximate execution duration.

For example:
If you run a test definition that takes 30 seconds to run on the first scheduled run, then on the second scheduled run the time left will start at 30 and count down to 0. If the test has been executing for 10 seconds the time left field will show 20 seconds remaining before the execution has completed.