How can I ensure defect synched to QC has the project value filled?

0 Likes

Problem:

How can I ensure defect synched to QC has the project value filled?

Resolution:

  • Product Name: StarTeam
  • Product Version: StarTeam 2006
  • Product Component: TD Synch
  • Platform/OS Version: All

Description:
How can I ensure defect synched to QC has the project value filled?




Answer/Solution:
If you do not specify the project field in StarTeam, whenever you have a new CR in StarTeam and would like to synch it to QC, you will end up with empty project value in QC. The remedy to this is to create a custom field with enumerated value in StarTeam that resembles the project values in QC. Once you have that, you can select the value each time you created a CR in StarTeam, and when you synch the CR, you will get the project field filled out in QC.




Author: Eyob Kidanmariam

Old KB# 27552
Comment List
Related