Is there a way to copy resources while copying the task within the workplan. We are on 9.62 and while we copy task the resources do not get copied and need to be added manually all over again.

Any help appreciated.

Tags:

  • Hi Urva,

    Resources assignments are part of task actuals, and are such are not copied when you copy over a task. 

    If you'd like to be able t copy resources over to new tasks but have empty actuals for them, feel free to submit an idea on PPM idea exchange. But in any case, resources' actuals should not be copied over to the new task.