Is there a way to exclude CPI from Non-Labor tasks when rolling up the work plan? We have found that entering Non-Labor Planned and Actual amounts is an easier way to track then going into the Financial Summary and entering by monthly blocks but our issue is that it is assigning a value of 1 for CPI because there is no way to track percent complete against Planned and Actual cost in the Cost tab, which we are manually entering. This presents an issue when calculating CPI because it is weighing theses tasks into the overall rollup of CPI and they are always going to be 1, which skews the CPI of the Labor.