QUESTION
----------------------------------
Why are my tests showing in the SilkCentral TestManager
activities section as running sequentially when they should be
running at the same time because I am using two execution
servers?
ANSWER
----------------------------------
To get your tests to run at the same time on two different
execution servers you need to create 2 folders with an execution
definition in each folder.
The tests will show as running sequentially (one will be queued
after the other in the activities section) if you only create one
folder with 2 executions definition inside this same folder.