Problem:

How do I force a process item be required at check-in of a file?

Resolution:

  • Product name: StarTeam
  • Product Version: 2008R2
  • Product Component: Server
  • Platform/OS Version: Windows 2003

Description:
How do I enforce a process item be selected upon a file being checked-in or added to StarTeam?


Answer/Solution:

To require use of process items at check-in, and specify which types to use

  1. Choose Project Properties and click the Process Rules tab in the Project Properties dialog box.
  2. Check Require Selection Of Process Items When Files Are Added Or Checked In.
  3. Check which types of items you want to allow for use as process items. (See below.)

To permit the use of change requests as process items

  1. Check Permit Selection Of Change Requests As Process Items.
  2. Do one of the following:
  • Check Open to use only change requests with Open status.
  • Check In Progress to use only change requests with In Progress status.
  • Check both Open and In Progress to use only change requests with either of these statuses.
  • Uncheck both Open and In Progress to allow any change request to be used as a process item, regardless of status.