How can I sync only a defect with a particular value in the project field?

0 Likes

Problem:

How can I sync only a defect with a particular value in the project field?

Resolution:

  • Product Name: StarTeam
  • Product Version: StarTeam 2006
  • Product Component: TD Synch
  • Platform/OS Version: All

Description:
How can I sync only a defect with a particular value in the project field?



Answer/Solution:
Suppose you have the following scenario.
In QC, you have a defect or defects with project field set to Project A.
In QC, you have a defect or defects with project field set to Project B.
You would like to Synch only Project A.

The above scenario can simply be achieved by adding the following option.
mtd_project1=ProjectA
If the above option is commented or left without a value all defects regardless of the value in the project field will be synchronized.



Author: Eyob Kidanmariam

Old KB# 27550