Test Case Status

In which cases i can keep my test script as "Not completed" Status in test set (Quality Center).

is it same like "Blocked"?

Please give me some example.
0 Likes
1 Reply
Highlighted
Absent Member.
Absent Member.

You can keep it in "Not completed" when part of the test case has been completed and you need to wait for sometime before executing the rest.

For example, you may do some transactions and then wait for a day for some batch jobs to run and then verify stuff on some tables. So, while you are waiting for the batch jobs to run, you can keep the test case in "Not completed" status, and then pass/fail it after the job runs.
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.