UCMDB Federation Question

Hi,

The customer is using the old version of UCMDB (v8.06) and we are using federation to push this data to Service Manager. We have a Scheduler which has 3 jobs added to it, the count of CIs in the TQLs for these 3 jobs is 20K. Now my question is when scheduler runs, the time taken to run the jobs should be equivalent to sync 20K CIs or the delta(changes) for these CIs?

Regards,
Puneet
Regards
Puneet

If you find this reply helpful, Click the KUDOS button on the bottom to say 'Thanks'
0 Likes
2 Replies
Highlighted
Absent Member.. Absent Member..
Absent Member..

Re: UCMDB Federation Question

Hi,
when you schedule the integration Jobs, you have the option of doing a full sync or changes sync, it is based on that
0 Likes
Highlighted
Acclaimed Contributor.. Acclaimed Contributor..
Acclaimed Contributor..

Re: UCMDB Federation Question

Hi,

You are right, in case schedule time will be less than time needed to sync 20K CIs you'll be in resource starvation situation.

Keep in mind that you could schedule diff and run full sync manually.

You also need to keep in mind discovery frequency. In case, discovery runs once a day, sync running twice won't bring any benefits...

 

Regards
-Dmitry Gomel, PMP
Click the Like button at the bottom to say 'Thanks'.
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.