Hi,

We are planning an upgrade of one of our oldest DP servers from 8.10 to 10.30. It's a tiny DP environment, a dozen jobs, with only two servers making up the cell, one Windows cell/installation physical server, one Linux client/installation VM server.

Question I have is what's the preferred method of backup prior to the upgrade to give the easiest backout if required, specifically the Windows physical cell manager? Unlike when we upgraded DP 7 to DP 9 where we found a nice simple RUNBOOK doc which showed backup/backout tasks prior to the upgrade, we've not found anything else we could use.

We have found a copy locally of the original DP 8.10 code (and 8.12 patch), so can reinstall if required as a new install. So our theory for the upgrade/backout would be if 10.30 upgrade fails and leaves DP unavailable:

  • prior to upgrade, run an IDB backup
  • shutdown DP & ensure no outstanding DP processes
  • create local copies of ProgramData\Omniback & Program Files\Omniback
  • perform upgrade, and if it fails...
  • uninstall 10.30
  • reinstall 8.10 & patch
  • recover to IDB backup taken prior to upgrade
  • talk to MicroFocus with the errors during the upgrade

Anything else we need to think about?

Thanks,

Andy

0 Likes
1 Solution

Accepted Solutions
Micro Focus Expert
Micro Focus Expert

Re: DP 8.10 to 10.30 Backout Plan?

Jump to solution

Hi @Andy___H1

That is your choice. I still recommend to follow the upgrade path 8.1x --> 9.00 --> 9.09 --> 10.x

But, if you see that it's a big deal and do not worth it you can try the upgrade directly. This is documented as supported. I am just telling you my experiences. 

Regards, 

Andres Fallas Salazar
Customer Support Engineer

If you find that this or any other post resolves your issue, please be sure to mark it as an accepted solution.
If you are satisfied with anyone’s response please remember to give them a LIKE by clicking on the bottom at the left of the post and show your appreciation.

View solution in original post

4 Replies
Micro Focus Expert
Micro Focus Expert

Re: DP 8.10 to 10.30 Backout Plan?

Jump to solution

The backout plan looks good. The only thing I would change is the upgrade path. 

Upgrading from DP 8.x to DP 10.x, it's supported, but for my experience newer goes well. 

I prefer to do this: 8.x --> 9.00 --> 9.09 --> 10.x

This is more reliable and easier to rollback in case of issues in any of this version. So, after each successful upgrade/patching, take an IDB backup, so you can come back to this point. 

Regards, 

Andres Fallas Salazar
Customer Support Engineer

If you find that this or any other post resolves your issue, please be sure to mark it as an accepted solution.
If you are satisfied with anyone’s response please remember to give them a LIKE by clicking on the bottom at the left of the post and show your appreciation.
Andy___H1 Super Contributor.
Super Contributor.

Re: DP 8.10 to 10.30 Backout Plan?

Jump to solution

Hi Andres,

Thanks for your reply.

The thing in our favour I suppose for a direct upgrade is this DP only has two servers which make up the whole cell, and only 6 filesystem backup jobs. So in terms of complexity and integrations, it has neither, this is practically as close to a native upgrade of an empty DP 8 to DP 10 you could get. Given this info, would you still recommend we go for a staged upgrade of DP 8-9-10?

Thanks,

Andy

0 Likes
Micro Focus Expert
Micro Focus Expert

Re: DP 8.10 to 10.30 Backout Plan?

Jump to solution

Hi @Andy___H1

That is your choice. I still recommend to follow the upgrade path 8.1x --> 9.00 --> 9.09 --> 10.x

But, if you see that it's a big deal and do not worth it you can try the upgrade directly. This is documented as supported. I am just telling you my experiences. 

Regards, 

Andres Fallas Salazar
Customer Support Engineer

If you find that this or any other post resolves your issue, please be sure to mark it as an accepted solution.
If you are satisfied with anyone’s response please remember to give them a LIKE by clicking on the bottom at the left of the post and show your appreciation.

View solution in original post

Andy___H1 Super Contributor.
Super Contributor.

Re: DP 8.10 to 10.30 Backout Plan?

Jump to solution

Hi Andres,

Thanks for the help and advice, I'd agree with you and your experiences, we'll plan for a multi-stage upgrade. It shouldn't take long to process each upgrade as our IDB is so small, so should get them all done in one day.

Cheers,

Andy

The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.