good morning,

with mainframe express I could launch 3 jobs A, B, C and they were executed one in queue to the other

MFECL /RUNEXE %PRJ% MFJCL.EXE %JCLDIR%\A.JCL /SUBMIT
MFECL /RUNEXE %PRJ% MFJCL.EXE %JCLDIR%\B.JCL /SUBMIT
MFECL /RUNEXE %PRJ% MFJCL.EXE %JCLDIR%\C.JCL /SUBMIT

in enterprise developer i have found command cassub (already present in mfe):

cassub -j %JCLLIB%\A.JCL -R%REGION_NAME%
cassub -j %JCLLIB%\B.JCL -R%REGION_NAME%
cassub -j %JCLLIB%\C.JCL -R%REGION_NAME%

in this case the jobs start almost simultaneously, isn't there a system to launch jcls in sequence so that the next one starts only if the previous one is finished?

 

thanks

0 Likes
1 Solution

Accepted Solutions
Highlighted
Micro Focus Expert
Micro Focus Expert

Re: cassub alternative

Jump to solution
Whether jobs are processed in series or parallel has nothing to do with how they're submitted (unless you wait until the current job finishes before submitting the next one). It's purely a matter of whether there's an available initiator to run a queued job.

The simplest way to have your three jobs run serially is to put them in the same job class, and only start one initiator for that class.

The set of initiators available at region startup is configured on the JES tab of the server properties in the Enterprise Server Administration web UI. The job class is specified on the JOB card in the JCL, of course.

There are other alternatives, such as using a scheduler and MFBSI (Micro Focus Batch Scheduler Integration). It's actually possible to build a simple scheduler with Windows command files. But using job class and a single initiator is the simplest, and most mainframe-like, approach.

1 Reply
Highlighted
Micro Focus Expert
Micro Focus Expert

Re: cassub alternative

Jump to solution
Whether jobs are processed in series or parallel has nothing to do with how they're submitted (unless you wait until the current job finishes before submitting the next one). It's purely a matter of whether there's an available initiator to run a queued job.

The simplest way to have your three jobs run serially is to put them in the same job class, and only start one initiator for that class.

The set of initiators available at region startup is configured on the JES tab of the server properties in the Enterprise Server Administration web UI. The job class is specified on the JOB card in the JCL, of course.

There are other alternatives, such as using a scheduler and MFBSI (Micro Focus Batch Scheduler Integration). It's actually possible to build a simple scheduler with Windows command files. But using job class and a single initiator is the simplest, and most mainframe-like, approach.

The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.