I have a GroupWise move/upgrade project in the works, and would appreciate any comments or suggestions. Here's the scenario: The existing GW system spans three physical locations, each with a single domain and PO. Total user count is about 200. All systems are running NW65 SP8 and GW 8.0.3. Let's call these locations A, B and C:

A hosts A-DOM A-PO A-LIB WebAccess GWIA (Primary domain)
B hosts B-DOM B-PO B-LIB
C hosts C-DOM C-PO C-LIB

The company is adding a new office, location D. Initially some (but not all) users will be moving from A to D. New server hardware has been purchased for D, so the intent is to make D the new primary domain, and to host GWIA and WebAccess from there. Of course I want to make the move to GW 2012 on OES 11 as part of this transition.

The extra fun comes from the fact that there is heavy use of DMS, and the document libraries are external to the POs as Novell once recommended as a best practice... 😉

Can I simply install a new OES 11 server at D, join the tree, and install GW 2012 into the existing system? Or do I need to install GW 8 on the OES server, add it as a new domain to the existing system, promote it to primary domain, then upgrade in place to GW 2012?

There are fast, stable VPN links between the locations, so I'm not too worried about doing user moves for the people who are relocating. But what about the documents stored in the libraries at A, B and C?

Another possibility that occurs to me is to move the whole A system to D and do an upgrade there, then allow the remaining users at A to connect remotely. Eventually the office at A will be closed and all those users will end up at D anyway. Is there any advantage to this approach, which will let me do the tried-and-true Netware to Linux migration? (Yes, I have Danita's book!)

Thanks in advance for your help.
Labels (2)
0 Likes
2 Replies
Highlighted
Absent Member.
Absent Member.

Re: YaUT - Yet Another Upgrade Thread

I think I answered part of my own question; am I correct that I can't just add the GW 2012 server into the existing system because the primary domain must be the most recent major revision? So I could go the route I described second, adding a new GW8 domain & PO on the new OES server, then promoting it to be the primary domain, then upgrading it to 2012?

Can I add WebAccess and GWIA on the new server after I do the domain/po upgrade, or do I have to install them as the GW8 versions first and then upgrade?
0 Likes
Highlighted
Absent Member.
Absent Member.

Re: YaUT - Yet Another Upgrade Thread

jimcooper wrote:

> I think I answered part of my own question; am I correct that I can't just add
> the GW 2012 server into the existing system because the primary domain must be
> the most recent major revision? So I could go the route I described second,
> adding a new GW8 domain & PO on the new OES server, then promoting it to be
> the primary domain, then upgrading it to 2012?


Correct

> Can I add WebAccess and GWIA on the new server after I do the domain/po
> upgrade, or do I have to install them as the GW8 versions first and then
> upgrade?


You can just add them. However, only GW2012 users can use that WebAccess and
the GWIA cannot act as a POP/IMAP client for GW8 POS.


--
Danita
Novell Knowledge Partner
Do you have Willem Bagchus' GW 2012 Admin Guide?
http://www.facebook.com/caledonia.net
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.