Anyway to migrate project include workplan and actual data

We had enhance new project type including form and workflow.

We can use special command to create project from existin project to copy data (migration) but how to copy workplan data with actual from existing to new one?

Please help

 

Best Regards

Aphiwat

0 Likes
1 Reply
Highlighted
Micro Focus Expert
Micro Focus Expert

Hello Aphiwat,
You can download the existing workplan to a microfsoft project plan (.mpp) file and upload the same to new project. This will retain the entire structure along with resource allocation to tasks.

I am not sure about actuals though. However on new project you can always add a manual entry in financial summary for the actuals which have been already calculated in old projects.

Let me know if this helps.

Thanks,
Mehul Shah
Microfocus SaaS Operations Lead

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.