CPI and SPI calculation without a proper work plan Baseline

Hi there,

I am wondering how the work plan CPI and SPI values are calculated when no proper work plan baseline is created.

In other words, my work plan is ACTIVE, I have planned and actual costs set up, yet I have not created any baseline.

In this situation, can the CPI and SPI ever show any value? If Yes, does it simply use the active work plan as baseline "0"?

Cheers,

Fred

0 Likes
1 Reply
Erik Cole Acclaimed Contributor.
Acclaimed Contributor.

Re: CPI and SPI calculation without a proper work plan Baseline

All the earned value metrics are all about comparing to a plan. Without a baseline, it has nothing to compare performance to.

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.