Change formula for project health

Jump to solution

Hi Everyone,

 

I have a question related to projects, is there any way to change the project health calculation?

 

I want to do it by a customized formula instead of the default process of PPM.

0 Likes
1 Solution

Accepted Solutions
Highlighted
Absent Member.
Absent Member.

Re: Change formula for project health

Jump to solution

Hi Gerardo,

there is no OOTB way to change default calculation.

However..

I making changes with calculation of Cost Health. It is "hard" customization on the database layer. But I don't recommend this way.

 

Regards

 

Radim

 

View solution in original post

0 Likes
2 Replies
Highlighted
Absent Member.
Absent Member.

Re: Change formula for project health

Jump to solution

Hi Gerardo,

there is no OOTB way to change default calculation.

However..

I making changes with calculation of Cost Health. It is "hard" customization on the database layer. But I don't recommend this way.

 

Regards

 

Radim

 

View solution in original post

0 Likes
Highlighted
Absent Member.. Absent Member..
Absent Member..

Re: Change formula for project health

Jump to solution

If you have a solid business justification for this you could submit an ER or contact PSO as well.

-- Remember to give Kudos to answers! (click the KUDOS star)
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.