Hi,

Is there a way to change the work plan default view from Quick View to Schedule view in 9.3x? I know once the plan is changed, per project, the view will stay on the select preference, but I would like to change it to the schedule view for the first time you open a project.

Thanks!

0 Likes
2 Replies
Absent Member.. alex-h Absent Member..
Absent Member..

Re: Change work plan default view

Hello,

Same problem here on PPM 9.32.0003.

We simply want to completely disable "Quick View" page, because it's not a reliable page. (Not possible to create/move Milestones, etc...).

I've investigated the problem and we have no option to change the default view, nor disable Quick View Page.

 

Kind regards,

Alex-H

0 Likes
Highlighted
Outstanding Contributor.. Loc_Nguyen_PPM Outstanding Contributor..
Outstanding Contributor..

Re: Change work plan default view

Hi,

You can try

1. Stop all nodes
2. Open \server\<your server>\deploy\itg.war\WEB-INF\conf\defaultWorkPlanSettings.properties
3. Change values for parameter “workplan.selectedViewName” from “quickView” to “scheduleView” (do it on every nodes in your instance).
4. Start all nodes.

Regards,

“HP Support
If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.