Team, is it possible to configure the view of the workplan portlet in the Project Summary section of the Project Overview? This is the Gantt view of the workplan on the Overview. 

 

We can manipulate the Gantt View when editing thru the workplan (changing the view to Gantt View).  We thought this would carry over to the Gantt on the Project Overview page but it remains the same.

 

Please see attached. 

One project  has the work plan date span as 'MONTH DAY' but another has 2 rows of dates, MONTH on top then individual dates on 2nd row.

 

Can this be changed or what is controlling this span?

Appreciate your help.

Frank

0 Likes
1 Solution

Accepted Solutions
Absent Member.. randull Absent Member..
Absent Member..

Re: Configure date span on work plan portlet on Project Overview page

Jump to solution

Hi Frank,

 

You are correct. You can check the setting of the work plan portlet for the project overview on Open > Administration > Portlet Definitions >  Configure portlet definitions.

 

Unfortunately, there aren't so much things that you can configure on this portlet.

Best regards,
Randall

-- Remember to give Kudos to answers! (click the KUDOS star)
"If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
0 Likes
3 Replies
Absent Member.. randull Absent Member..
Absent Member..

Re: Configure date span on work plan portlet on Project Overview page

Jump to solution

Hi Frankie,

Unfortunately, it is not possible right now to have the date span on the project overview for the work plan portlet.

But, it sounds like a good Enhancement, you can submit a new one here,

 

https://support.openview.hp.com/enhancement/do/main

Best regards,
Randall

-- Remember to give Kudos to answers! (click the KUDOS star)
"If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
0 Likes
Frankie_Kings Super Contributor.
Super Contributor.

Re: Configure date span on work plan portlet on Project Overview page

Jump to solution

Randall, so is the portlet on the overview then defaulting by some other settings?  Just curious as to why 1 project would have one view and another project's view would be  a different.  Could it be based on the Start/End of the project and that automatically sets the date span view on the portlet.

Thanks for the information and yes we may submit an enhancement for this.

Frank

0 Likes
Absent Member.. randull Absent Member..
Absent Member..

Re: Configure date span on work plan portlet on Project Overview page

Jump to solution

Hi Frank,

 

You are correct. You can check the setting of the work plan portlet for the project overview on Open > Administration > Portlet Definitions >  Configure portlet definitions.

 

Unfortunately, there aren't so much things that you can configure on this portlet.

Best regards,
Randall

-- Remember to give Kudos to answers! (click the KUDOS star)
"If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.