Hello wxperts,

 

I have few question. Hope you can help me out.

 

1) Some project tasks show exception that % complete is not provided by some resources. I see that similar sort of task (same duration and resources) in the same project is also having 0% complete but does not show any exception. Why?

 

2) If the sceduled duration of a task is 10 hrs and we assigned one resource it. Can we stop resource from entering more than 10 hours for the task? or any warnings?

 

3) Do we have any HP provided protlet which shows to a resource manager as how resources are entering their time in the projects CAP Vs Expense. I think it calls for custom query but in case we have any?

 

4) We are moving to IE#11. I tested it seems to work fine. But do you see any issues using PPM V 9.12 and 9.20 on IE 11??

 

5) what does that mean if the project health is None. (nothing of Red,Green,Yellow)

 

 

Thanks

-Mohit

0 Likes
7 Replies
CGut Absent Member.
Absent Member.

Re: Few questions

1) https://softwaresupport.hp.com/group/softwaresupport/search-result/-/facetsearch/document/KM184420

 

There is some notes taken for the TM guide

 

(Used only for tasks) Your personal total percentage contribution toward completing a task or request, for the cumulative time you have reported on time sheets. Contributions of others are excluded. If this field is required for any tasks on the time sheet, red asterisks are displayed next to this field for those tasks and next to the Other Actuals tab name

 

Updates to your actuals data other than actual effort, such as % Complete, can be entered in either HP Time Management or HP Project Management, and are then automatically reflected in the other. In the time sheet, this data is entered on the Other Actuals tab

 

Page 152

In the Actual Effort in the Work Plan subsection in project settings , select the Track Actual
Effort per resource assignment check box (it is selected by default).If you select the subordinate Require resources to enter % Complete along with actual effort check box, resources must specify a non-zero value for % Complete when they specify actual effort on time sheets or elsewhere. (This check box is selected by default.)If you select the subordinate Track Estimated Remaining Effort per resource assignment check box, resources must report time at the Task level specified in step b on page 153. (By default, this check box is not selected.)


2)   Under the After a task is complete, allow time to be logged: heading, specify one of the following options for whether and how long time can be logged against a task after its Actual Finish Date (its completion
date):
A number of Day(s) more
A number of Time period(s) more. To allow logging until the end of
the time period in which the task is completed, enter 0.
Any time after the task is completed.
Do not allow.

 

3) Seems to be a custom portlet that you can creat with a DBA help.

 

4) IE 11 is not supported in PPM 9.10 nor 9.20. You should upgrade to PPM 9.30 to use it.

 

5) The project’s schedule health indicator is a simple color-coded indicator of the health of a work plan. A project only has a schedule health indicator when the work plan is Active; it disappears when the work plan is completed or put On Hold.

 

You can find more information about timesheets in the TM user guied attached.

 

Best Regards,

Carolina.


“HP Support
If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
0 Likes
SandraL Valued Contributor.
Valued Contributor.

Re: Few questions

As long as you enable the Compatibility setting in Internet Explorer for your PPM URL, we have been able to run PPM 9.14 with the newer levels of IE successfully.

 

Without the Compatibility setting in IE enabled, our users have encountered a number of strange errors.

0 Likes
CGut Absent Member.
Absent Member.

Re: Few questions

Hi Sandra, 

 

It could be a possible workaround to use IE 11 in PPM 9.14, just keep in mind if you present any issues, you should test it with a compatibility settings as IE 11 is not supported in this PPM version. 

 

 

Best Regards, 

Carolina. 


“HP Support
If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
0 Likes
Absent Member.. Mohit_Agrawal Absent Member..
Absent Member..

Re: Few questions

Hi Carolina,

 

If project settings say that "Require % complete" then why not resources are prompted to enter the % complete for the task when they fill up time sheet?

I see that over 20 resources charged time and none of them entered % for this...that's why the task shows exception that "Some of the resources have not entered % Complete"

 

what's the reason? How do I manually correct it?

 

thanks

0 Likes
CGut Absent Member.
Absent Member.

Re: Few questions

If you select the subordinate Require resources to enter % Complete along with actual effort check box, resources must specify a non-zero value for % Complete


When they specify actual effort on time sheets or elsewhere. (This check box is selected by default.)

Your personal total percentage contribution toward completing a task or request, for the cumulative time you have reported on time sheets. Contributions of others are excluded. If this field is required for any tasks on the time sheet, red asterisks are displayed next to this field for those tasks and next to the
Other Actuals tab name.

 

Best Regards,

Carolina


“HP Support
If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
0 Likes
Absent Member.. Mohit_Agrawal Absent Member..
Absent Member..

Re: Few questions

Carolina,

 

That's what I am saying. If it is required that resources must input the %complete then why they are not forced to enter while filling time sheet.

Please see work plan image where task 3 is Red and Task 4 is not.

You see task#3 the total % complete is 0...why? (If %required is must for resources)

And task#4 is also not having any % complete even then it is not Red..why? (it follows the same policy)

 

Hope you understand my question now..

 

Regards

Mohit

0 Likes
CGut Absent Member.
Absent Member.

Re: Few questions

Hi Mohit,

 

Are you in PPM 9.12? Seems to be a known issue in this version, Please take a look on the following defect. It was fixed in PPM 9.14.0004. You should upgrade your PPM version to 9.2x or 9.3x due PPM 9.1x end of support for this release is in October 31th, 2015.

 

https://softwaresupport.hp.com/group/softwaresupport/search-result/-/facetsearch/document/LID/QCCR1L45131

 

Best Regards,

Carolina.

 

 


“HP Support
If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.