Highlighted
Shravan Kathuri Absent Member.
Absent Member.
345 views

Getting wrong values for project schedule and cost health columns

Hi,

For some of the closed projects, we have observed that scheduled health and cost health columns of PM_project_rollup table is having value 'Green'. What could be the problem.
Am I referring correct table for getting project schedule,cost,issue health information.

Can anyone please help me.

Thanks
Shravan.
0 Likes
7 Replies
Celil Absent Member.
Absent Member.

Re: Getting wrong values for project schedule and cost health columns

Hi Shravan,

You didn't describe the problem: You said in PM_project_rollup table scheduled health and cost health columns are 'Green'. What do the project show in end user screen ?

In these case please detail that; When the project is running, shows Yellow then when you close the project, it's trun to Green ? or remain Yellow ? or you expecting difirent value ?

In addition to that, you are using right table.

Celil
Celil

IT Governance Professional
& PPM Solution Architect
0 Likes
Shravan Kathuri Absent Member.
Absent Member.

Re: Getting wrong values for project schedule and cost health columns

Hi Celil,

Thanks for your quick response. Actually some are projects are already closed. when we open thse projects , in front end, nothing is displayed for scheduled health , but in pm_project_rollup,
there is value "Green" for "scheduled_health_indicator". why it is showing "green" in the table.

Can we use pm_project_rollup table for overall health also?

Thanks
Shravan.
0 Likes
Absent Member.. Abdullah Rafiq Absent Member..
Absent Member..

Re: Getting wrong values for project schedule and cost health columns

Hi Sharavan,
One thing to possibly check might be the status of the workplan
0 Likes
Shravan Kathuri Absent Member.
Absent Member.

Re: Getting wrong values for project schedule and cost health columns

I have even checked the status of workplan, but it is in complete status
0 Likes
Shravan Kathuri Absent Member.
Absent Member.

Re: Getting wrong values for project schedule and cost health columns

Hi,

Anyone has any idea about this issue.

Thanks
Shravan.
0 Likes
Absent Member.. Edtroleis Absent Member..
Absent Member..

Re: Getting wrong values for project schedule and cost health columns

The health into a project is composed to three values:
- schedule
- issue
- cost and earned value

Are you using issue or earned value?

Regards.
0 Likes
Super Contributor.. JodieOndrejka Super Contributor..
Super Contributor..

Re: Getting wrong values for project schedule and cost health columns

Have you found an answer to this?  We're seeing the same problem.  We're running 9.31

 

Thank you

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.