How to populate future time periods in KNTA_PERIODS

Hi All

We have the report which is generating project data by comapring the period_id  from KNTA_PERIODs  and = finish_date_period from PM_PROJECTS. We found thta there are no period reference of 2018 in KNTA_PERIODS , Hence  the report is blanked out since no data is fetched by the underlying query.

Please advice if I can run sh kGenPeriods.sh to get this fixed.

Thanks,

Taraka

 

0 Likes
1 Reply
Highlighted
Shiwan Respected Contributor.
Respected Contributor.

Re: How to populate future time periods in KNTA_PERIODS

Hello Taraka

Which version are you using? If it is 9.3, you can go to Open --> Administration --> Open Administration Console, once it opens; Go to Administration Task --> Generate Fiscal Periods and do the rest.

Regards,

Shiwan Agrawal

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.