Impact of Configuring Holidays to a Calendar

Hi,

We are currently on PPM v9.32. We wanted to understand the impact of newly configuring holidays on the default region calendar which has been in use for a few years now. What will be the possible impacts on the existing forecast calculations and utilizations.

Any details in this regard would be helpful.

Thanks.

0 Likes
2 Replies
Outstanding Contributor.. Amishra Outstanding Contributor..
Outstanding Contributor..

Re: Impact of Configuring Holidays to a Calendar

hello,

If the resources are using regional calendards then, yes, certainly there will be impact on the capacity of the resources. If they are assigned to a week where there is a public holiday, then it will be shown as over-allocation. The capacity will be reduced as well. 

I dont think there will be any impact on the forecast as such. 

 

Ajay

 

Regards,
Ajay Mishra
0 Likes
ArunKr Super Contributor.
Super Contributor.

Re: Impact of Configuring Holidays to a Calendar

 

When creating holidays in the existing default Calendars used by all the resources.

Example for existing position: if PM forecasts 1 FTE,

  • before the change = 1.00 FTE
  • after the change    = 1.05 FTE

if PM forecast by hours:

  • before the change = 152 hours
  • after the change = 152 hours

 

The new allocation (of the resources) are also based on the newly updated calendar. If the resources were allocated during the new calendar holiday time, they would show as over allocated. or if you mark any holidays as working day, it would show as under allocation for the committed resources

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.