Link tasks via predecessors
Guys
I have created work plan in HP PPM and trying to link task 1 and 2 with a predecessor FS with 0 lag.
For example
Task 1 - 10 days - 15 Sep - 28 Sep
Task 2 - 20 days - 15 Sep - 12 Oct (by default the start date is still showing as 15 Sep even though i have linked this to Task 1 with FS relationship). The status of this task is showing as pending predecessor
I believe, as we do in MS project, tast 2 should be automatically calculated to start from 1 Oct due to predecessor link but it's not changing automatically
Am i missing something here, please help/advice
Thanks
1 Reply
MIF

Commodore
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
2018-09-17
10:25
Hi,
You should click schedule workplan button in the toolbar to make ppm plan appropriately.
Regards,
--Remember to give Kudos if you like the solution.
Murat Akbar
MIF Software & Consultancy - Istanbul