KiranDubbaka
New Member.
227 views

PPM Integration issue with MSP.

Hi,

 

We are having HP PPM 9.22 version and currently working on the  Integration of HP PPM with MicroSoft Project (2013). And ,we are taking an Integration mode as "Shared mode" . Where,

 

- Work breakdown information is controlled by Microsoft 

- Actuals tracking information is controlled by PPM 

 

But,  when we try to "Send Workplan to PPM"  the option itself is disabled in MSP. Hence, we are not able to send the Workplan created in MSP to HP PPM.

 

Could you please look into the issue and let us know the root cause?

 

For reference, I am attaching the screenshot of the option showing as disabled?

 

 

Thanks,

Kiran

0 Likes
1 Reply
Micro Focus Expert
Micro Focus Expert

Re: PPM Integration issue with MSP.

Hi Kiran,

 

It may be that this mpp file is not properly associated with the PPM Project. Could you share with us the content of the "Project Details" menu item?

 

Maybe someone removed the association to the PPM project; if that's the case, you'll be able to restore it from that menu.

 

Thanks,

Etienne.

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.