Is it possible to configure proper part-time employees in the HP PPM system? Those employees need to have less available capacity in the Resource Load access via the Staffing Profile assignment finder.

The best OOTB way to achieve adding part time employees is to add them to the resource pool and then manage the resource participation by setting it to 50%.
For example, if you have 8 h per day, which is 40 h per week for normal employees, if you set resource participation to 50%, then they will have 4h per day.

Labels (1)
0 Replies
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.