Absent Member.. randull Absent Member..
Absent Member..
47 views

PPM Support Tip: Project settings issue - cost and effort tab -> scheduled effort in work plan

 

Knowledge base article: KM00820025

Enhancement Request: QCCR1L54393

 

In project settings, under cost and effort tab -> scheduled effort in work plan users have initially selected following options:

 

1. The check box for 'Use Sceduled Effort during planning

2. Radio button for 'Automatically calculate Scheduled Effort'

3. Check box for 'Allow override of effort calculation mode in the work plan'.

 

After the project started, the user wants to change these settings to manual control mode for which we unchecked all these settings and selected the following settings:

 

1. The check box for 'Use Sceduled Effort during planning

2. Radio button for 'Manually enter scheduled effort per task assignment'

 

However, after changing this setting, at task level, the tasks are still in auto calculation mode. The manual mode is coming in only for the newly created tasks.

Best regards,
Randall

-- Remember to give Kudos to answers! (click the KUDOS star)
"If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
Labels (1)
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.