PPM Support Tip: Specifying the Sequence of Actuals Fields When Importing Tasks from PPM Center

Specifying the Sequence of Actuals Fields When Importing Tasks from PPM Center to Microsoft Project.

 

Enhanced Functionality on PPM 9.310001

 

With the updated Microsoft Project plug-in, you can specify the sequence of actuals fields to be inserted in the Microsoft Project. To specify the sequence:


1. Open the project in the Microsoft Project.
2. In the Add-Ins tab, select HP PPM Center > User Preferences.
3. In the Tasks Creation tab, Actual fields section, specify the sequence of the actuals fields. The actual field on the top will be inserted first while the actual field on the bottom will be inserted last.

 

 


You cannot specify the sequence of actuals fields unless you select the option Override PPM Project Settings.... If you select the option, it only applies to new tasks and is not applicable when you retrieve actuals from PPM. If you deselect the option, you have to follow the setting of Transfer actuals information in PPM project.


4. Click Save.

 

Best regards,
Randall

-- Remember to give Kudos to answers! (click the KUDOS star)
"If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
Labels (1)
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.