Highlighted
mike_se Contributor.
Contributor.
120 views

PPM Support Tip: Users need to be Participants/Stakeholders to see correct % Complete

A new KCS article was published: KM00473691

When viewing the Progress bar on the Project's Overall Status section, 0% shown to Users without a Project Management License

1. Login as User with a Project Management (PM) License.
2. Create a Project.
3. Create a Work Plan and add some Tasks and make one of them Complete.
4. The Project Progress bar shows the actual Percent Complete.
5. Now login as other User with non-PM License and view the Project; the Project Progress bar shows 0%.

Defect QCCR1L51723

Workaround: Add Project Participants and Stakeholders to those who do not have Project Management License.

“HP Support
If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
Labels (1)
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.