(PPM) Support tip: Using Region of Resource Pool when Calculating Forecast Labor Cost

 

In previous versions, when PPM calculates forecast labor cost from a staffing profile position, the region

used to pick up the cost rule is always the region of the staffing profile unless a resource is assigned to

the position.

 

In PPM 9.32, you can use the following server configuration parameter to decide to use the region of the

staffing profile or the region of the resource pool. You can configure this parameter in the

server.conf file or the Administration Console.

 

 

 

If you set this parameter to true, PPM uses the region of the resource pool specified for the position to pick up cost rule when calculating its forecast labor cost.

 

If you set this parameter to false, PPM uses the region of the staffing profile where the position

belong to pick up cost rule when calculating its forecast labor cost.

 

 

 

Best regards,
Randall

-- Remember to give Kudos to answers! (click the KUDOS star)
"If you find that this or any post resolves your issue, please be sure to mark it as an accepted solution.”
Labels (1)
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.