(PPM) support Tip: Cost violation is calculated as rounded-off values.

From Project Exceptions tab, the Cost Violation is calculated as rounded-off values.

For example, if the cost violation is 8,0001%,
percentage 8,0001% is rounded up to 9% in the calculation.

Scenarios:

a.

Actual = 10 829 08$
POR = 10 000 00
Apply in this case :
((Actual Cost - Plan of Record)/Plan of Record) * 100=(( 10 829 08– 1 000 000)/1 000 000)*100= 8,2908%
But  PPM rounds up to 8%.


b.

Actual = 1 080 125 $
POR = 1 000 000$
Apply in this case :
((Actual Cost - Plan of Record)/Plan of Record) * 100= (1 080 125 – 1 000 000)/1 000 000)*100= 8,0125%
But  PPM rounds up to 9%.

Please check "cost_violation.xlsx" attached.


Starting from 9.32.0001 the Cost violation percentage will be calculated as accurate value
while in cost exception the percentage is saved to have 3 decimals.

Labels (1)
Tags (1)
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.