Visitor.. rsm123
Visitor..
281 views

Some tasks' status information changes automatically

Hi Everyone,

 

We have a problem. Status information of some tasks in some projects changed automatically from In progress to Ready. We checked the Work Plan Audit Trail but we did not see a change to the about these tasks. We also checked the system logs, but we could not find anything about this change status information.Could it be the source of the problem that Schedule Services? We observed that the problem did not occur at regular intervals.

 

Thanks...

0 Likes
2 Replies
Outstanding Contributor.. Amishra Outstanding Contributor..
Outstanding Contributor..

Re: Some tasks' status information changes automatically

Did you find anything in the Task Audit trail, have a look there. Open task details > more > Task Audit Trail.

 

Regards,
Ajay Mishra
0 Likes
Micro Focus Expert
Micro Focus Expert

Re: Some tasks' status information changes automatically

Hi,

- Are the culprits tasks summary tasks or leaf tasks?

- Do you use timesheets on this project?

- How did you set the initial "In progress" status?

- Do you have any actuals for the task? Did someone set the % complete to 0% or remove the actual hours of the task? 

- If it is a summary task, was the status change the result of updates to its children tasks?

Thanks,

Etienne.

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.