Staffing profile Statistics section change end period fileds
Good morning
I've a question for staffing profile module in ppm 9.3.
When I change the field end period in statitics section in automatic all the allocation value in positions erases.
Why? It's a normally function by the module?
Is there a documentation where explain this beahvior?
I'm looking for in HP Project Management User’s Guide but I found nothing about this.
Here a screenshot
Thanks to all
Dzorzi

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
When you change the End period to later date than the existing period, it wont impact but if you change to earlier period, it will erase.
Example:
- Start Period: Jan-2017
- End Period: Sep-2017
- If you change the End Period to Aug-2017, it will erase the forecasts
- If you change the End Period to Dec-2017, no impact.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
Hello Dzorzi
Please refer attached document where I captured multiple scenarios.
Hope it helps.
Regards,
Shiwan Agrawal

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
Remaining Scenarios


- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
Thanks to all in the meantime
In the scenario than you have exposed in my case It not behaved so but in this mode:
The user changed the end period filed from Feb 2017 to Apr 2017 and the data were removed. It' very strange because the user brought forward the date...
Is There a guide or a manual where this is explained?