Update the Project Forecast

Hello,

I am trying to figure out how to update the forecast of our projects. Our current set up is we are calculating the forecasted labor cost from the staffing profile and entering the actuals manually as an added cost line in the financial summary.

What I would like is the forecast to be based on the manual actuals entered up until the present day and the forecasted budget from the staffing profile after that for the rest of the year. Is this possible?

Thanks in advance! 

0 Likes
1 Reply
CurtisD
New Member.

Re: Update the Project Forecast

This is what I am looking for:

EAC = AC + PCWR
 
with 
AC: The actual cost at the current time moment (i.e. AT = actual time)
PCWR:  Planned Cost of Work Remaining as an estimate for the future
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.