Team, we have workplan templates that consist of standard tasks with Generic Resource names that are used as placeholders.  Our process is for our Project Managers to create their projects with these templates and then update the generic spots with named resources.

 

All our Generic Resources (ex. Developer Generic) are in a resource pool.  

 

When a Project Manager tries to create a project with this template, the Generic Resources on the template DO NOT come into their project workplan.

 

It appears this has to do with the fact that the Project manager using the template is not a manager of the Generic Resource Pool. 

 

Our curent process is that we allow Managers, Leads or Subject Matter Experts the capability to create projects and use these workplan templates.  This could be over 100 plus people. 

 

Is there any other option available that would  allow control of resources in a resource pool?  There is not an option to add a 'group' as a Manager of a pool.

 

We didn't know if there could be a system setting or security access that would allow for this without having to individually designate all the potential managers of the pool?

 

Appreciate any advice or suggestions from the group on our situation or if others have ideas on other ways to handle the use of a Generic Resource in workplans. 

 

Thank you!

Frank

0 Likes
1 Solution

Accepted Solutions
Highlighted
Commodore
Commodore

Etienne,

Since we not pursue using Staffing Profiles for our resource/assignment process we know that limits us with how to manage assignments.  Our Project Management team is currently reviewing the Staffing options again. 

 

We may experiment with overriding the Assignment controls but not sure what other impacts that could open us up for but thank you for this suggestion.

 

We just wanted to know if we were missing any functionality around these 'generic resources' we want to use, and appreciate you pointing out the Staffing Profile option.

Thanks!

Frank

View solution in original post

0 Likes
4 Replies
Highlighted
Fleet Admiral
Fleet Admiral

Hi,

Do you have the setting enabled to only allow resources on the workplan that exist on the project's staffing profile?

Since you can assign roles to tasks, what value does assigning "generic resources" give you?

0 Likes
Highlighted
Micro Focus Expert
Micro Focus Expert

Hi Frank,

 

Another option (with a bit more overhead) is to put these generic resources in the Project's Staffing Profile.

 

Unless you ignore RM Assignment constraints (There's a parameter RM_OVERRIDE_ASSIGNMENT_CONTROLS that you can edit from the admin console to do so), then you can only use resources in the work plan that are either in the project's staffing profile or in a resource pool to which you (i.e. the project manager) is a resource pool manager.

 

Thanks,

Etienne.

Highlighted
Commodore
Commodore

Erik,

our current process does not include the use of Staffing Profiles.  I definitely know that option does help to standardize the whole resource/assignment to task process.  But our Project Management Dept. made the call to not using Profiles after determining that whole process would be too effort intensive for their department and our project managers.  (I'm only the system admin. and can only recommend the options...can't force them to take them)!

 

Also we have some managers (mostly on the operations side) that wanted Generic Resources directly assigned to them so they could see them in their capacity planning portlets.  This was to help them know the requested work so they could disperse out to their teams.

 

Putting these generic resources in one pool helped with large project plan templates that we are using.

 

But I hear our project team may be revisiting the Staffing profile process so here's hoping they see things differently this time as we are now experiencing some of the limitations of now following a system process for making task assignments.

 

Please let me know if you have any other information or suggestions that we may be able to use.

Thanks much.

Frank

 

 

0 Likes
Highlighted
Commodore
Commodore

Etienne,

Since we not pursue using Staffing Profiles for our resource/assignment process we know that limits us with how to manage assignments.  Our Project Management team is currently reviewing the Staffing options again. 

 

We may experiment with overriding the Assignment controls but not sure what other impacts that could open us up for but thank you for this suggestion.

 

We just wanted to know if we were missing any functionality around these 'generic resources' we want to use, and appreciate you pointing out the Staffing Profile option.

Thanks!

Frank

View solution in original post

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.