Why work plan planned (labour or non-labour) costs are not rolled up in the Financial summary table?

hi team,

the following question is really bugging me and I cannot find any guide or online litterature offering a clear explanation:

Why work plan planned (labour or non-labour) costs are not rolled up in the Financial summary table?

HP PPM 9.22

I must say that we are NOT using Staffing Profiles on our platform. Yet Time management is enabled and actuals from the work plan are correctly rolled up in to the Financial summary table.

I am attaching the Project Cost details print screen as illustration. We can clearly see that actuals from the work plan are listed under the Financial Summary, while the Planned costs ain't.

Why is my question.

Many thanks in advance,

Fred

0 Likes
1 Reply
Erik Cole Acclaimed Contributor.
Acclaimed Contributor.

Re: Why work plan planned (labour or non-labour) costs are not rolled up in the Financial summary ta

Hi,

Technically, the answer is that it's that way by design. Only staffing profile forecast labor costs roll into the financial summary, and only actual non-labor costs roll from the workplan.

I don't get their logic, and I've found it to be quirky & unsatisfactory as well.

The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.