MS Project Work Around

Hello All,

Is there a way other than MS Project Integration to synchronize the % complete? This is a pain point for our PM's as the timesheet data populates our actuals but causes duplicate effort to add the % complete.  We don't have our associates estimating remaining effort.

0 Likes
1 Reply
Adolfo_A_PPM Super Contributor.
Super Contributor.

Re: MS Project Work Around

Hello Kalim,

I hope you’re having a good day.

My name is Adolfo Alvarado from PPM team and I have been assigned to assist your thread related "MS Project Work Around

I was reviewing the "project management configuration guide" document and the page 37,  you can find the steps to configure the actual from the time management, I attached the document. 

Any questions or doubts please let me know 

Best Regards 

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.