Auto close change when the last task associated with the change is closed

Hi,

     I am using SM 9.30,

      We have a scenario where we have to auto close the change record when the all the tasks associated with the change are closed.

 

Please help on the same..

 

Thanks

0 Likes
3 Replies
DimitarPeychev Absent Member.
Absent Member.

Re: Auto close change when the last task associated with the change is closed

Hi,

 

 I found the oposite I think 🙂 -> Auto close change tasks

 

http://h30499.www3.hp.com/t5/HP-Service-Manager-Service/Auto-close-change-tasks/m-p/4659392/highlight/true#M44061

 

However my Idea is that this may be possible to be achived from

This behavior is set through the change phase definition.
Go to phase definition of the phase for which you do want to make the changes.

In the "Alerts/Open & Close Behavior" tab select the follow two radio buttons
1. "Close - open next phase or exit on last phase (no cancel)".
2.Open - prompt for update (no deferral)

 

and also another idea:

 

http://h30499.www3.hp.com/t5/HP-Service-Manager-Service/Auto-Skip-Phase-when-last-task-closes-by-problem-change/m-p/6041003/highlight/true#M99456

Auto Skip Phase when last task closes by problem/change scheduler

 

HP Support
If you find that this or any post resolved your issue, please be sure
to mark it as an accepted solution.
Please also give kudo if you find it interesting 🙂
0 Likes
Highlighted
Absent Member.. Federico Chaves Absent Member..
Absent Member..

Re: Auto close change when the last task associated with the change is closed

Hello,

 

are u using process designer? if not, in the phase definition record, you can check "close this phase" in the model/task section.

 

HTH.

 

 

Best Regards,

Federico Chaves
0 Likes
Absent Member.. John Stagaman Absent Member..
Absent Member..

Re: Auto close change when the last task associated with the change is closed

If you are using process designer, you can use the change the parent change status to 'value" when all tasks are closed option in the phase definition and add an automated transition to the next phase that executes when that status is set. (The option to automatically close when all tasks are closed doesn't appear to work with PD right now--9.33 PD4).

----------------------------------------------------
Kudos - what, where, how, and why
Want Good Answers? Ask Good Questions...
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.