Highlighted
Honored Contributor.. Honored Contributor..
Honored Contributor..
234 views

Close Phase and Change Task Closure

I have a reqwuirement where an RFC has to move from "Deployment" phase to "Build and Test" phase. This is a manual transition available only for change managers and Sysadmins. During this transition there is a validation message that prevents this transition. This is a maual task and not a task created using Task planner. 

"This Change may not leave the current phase until the following tasks are closed: T12345"

 

How can override this validation only for Change Managers  & Sysadmins? We are using 9.4 codeless.

 

 

 

 

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.