There is a known issue where task plans are not included as part of the change model UNL neither using the Script Utility nor Export/Unload option (“Use Data Map”).

 

There is an ER already opened for this(QCCR1E127787), link below:

 

https://softwaresupport.hp.com/group/softwaresupport/search-result/-/facetsearch/document/LID/QCCR1E127787

 

According to CPE,  “since task is not in same file as change model  unload does not contain it, customer can export related task by themselves to work around it”

 

However, it does not give much detail on where are stored those tasks so it can be confusing.

 

Workaround:

The records displayed in the component are saved into that table under the file name "ChangeModel". In other words, you should add an unl of the “changePlan” record to export the whole configuration (ChangeModel and Tasks).

 

-Jose Pablo Mora-

Labels (1)
3 Replies
Highlighted
Honored Contributor.. Honored Contributor..
Honored Contributor..

Re: (SM)Support Tip:How to unload Request Model Task Plan

Is there an equivalent to the changePlan for requests so that we can unload requestModels and tasks?
0 Likes
Highlighted
Absent Member.. Absent Member..
Absent Member..

Re: (SM)Support Tip:How to unload Request Model Task Plan

Note that when unloading Task Plans from the changePlan table, you want to filter them to only include those plans associated with Change Models and exclude the plans associated with actual changes. If you don't, you may load task plans into the target system which may adversely impact existing or future change records.

----------------------------------------------------
Kudos - what, where, how, and why
Want Good Answers? Ask Good Questions...
Highlighted
Absent Member.. Absent Member..
Absent Member..

Re: (SM)Support Tip:How to unload Request Model Task Plan

Is there an equivalent to the changePlan for requests so that we can unload requestModels and tasks?

 

Both Request Model and Change Model task plans are stored in the changePlan table. The functionality built for change was leveraged for the new request module.

----------------------------------------------------
Kudos - what, where, how, and why
Want Good Answers? Ask Good Questions...
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.