Hi,

Is there a need for any manual or additional steps on the request module when upgrade from 9.34 PD to 9.51 codeless ?

As per understanding, Process Desginer version of request module only started in 9.40, and in 9.34 it is still using the old classic quote, line item, order and maintenance.

In the 9.51 upgrade document there isn't any steps or topic about upgrade of request module or the open new request catalog connector. Do like to check does that mean in the upgrade unity package it had being scripted to auto upgrade 9.34 classic to new PD request module and no additional effort is required?

Kindly advice can we upgrade from 9.34 to 9.51 directly or do we need to upgrade to 9.40 then to 9.51?

Regards

Soong 

Regards
Soong
0 Likes
1 Solution

Accepted Solutions
Highlighted
Micro Focus Expert
Micro Focus Expert

Re: Upgrade steps for request module from 9.34PD to 9.51

Jump to solution

Yes, the upgrade should automatically convert those to the corresponding items in Request Fulfillment. You will also be upgrading the SRC to 9.50 so the SRC will know to interact with the new module. If you have customizations to your current Request Management module, there may be some things that need to be handled during the conflict resolution phase of the upgrade, but that is the usually the case with any module when customizations are present.

If you find that this or any other post resolves your issue, please remember to click "Accept as Solution". If you are satisfied with anyone’s response, please remember to give them KUDOS by clicking on the "thumbs up" at the bottom left of the post to show your appreciation.

View solution in original post

0 Likes
4 Replies
Highlighted
Acclaimed Contributor.
Acclaimed Contributor.

Re: Upgrade steps for request module from 9.34PD to 9.51

Jump to solution

Hello Soongwc,

hope you are doing fine.

our suggestion to proceed with this upgrade, is going to 9.40 first and then to 9.51 in order to avoid issues in the proceess, in case you need documentation please let me share with you a link with guides may be helpful for you:

https://softwaresupport.hpe.com/group/softwaresupport/search-result/-/facetsearch/document/KM01294561?lang=es&cc=es&hpappid=OSP

there you can find any kind of guide, you can save the link for future information as well. Hope it helps

Carlos Villalobos R
Customer Support Engineer
If you find that this or any other post resolves your issue, please be sure to mark it as an accepted solution.
If you are satisfied with anyone’s response please remember to give them a KUDOS by clicking on the STAR at the bottom left of the post and show your appreciation.
0 Likes
Highlighted
Micro Focus Expert
Micro Focus Expert

Re: Upgrade steps for request module from 9.34PD to 9.51

Jump to solution

There is nothing wrong with going from 9.34 with PDCP4 directly to 9.50 (you can then patch to 9.51). You don't need to upgrade to 9.40 first since this will add an additional unnecessary step. Please keep in mind that if you go from 9.34 with Process Designer Content Pack 4 (9.30.3), you need to go to Codeless mode in 9.50. This should convert your Request Management module to Request Fulfillment.

However, if you have Process Designer Content Pack 3 (9.30.2), then you must go to Hybrid Mode in 9.50, which will involve some manual migration tasks after the upgrade is completed. If you have NO Process Designer installed on 9.34, you also must go to Hybrid mode in 9.50. Additional information can be found in the SM Upgrade Guide, which is attached to this post.

If you find that this or any other post resolves your issue, please remember to click "Accept as Solution". If you are satisfied with anyone’s response, please remember to give them KUDOS by clicking on the "thumbs up" at the bottom left of the post to show your appreciation.
0 Likes
Highlighted
Super Contributor.. Super Contributor..
Super Contributor..

Re: Upgrade steps for request module from 9.34PD to 9.51

Jump to solution

Hi  Mike_Gross,

Thanks for advice, the current system is 9.34P4, and after reading your advice i'm thinking of going ot 9.50 codeless directly but do like to clarify on the following  

"This should convert your Request Management module to Request Fulfillment."

this convertation does it auto populate all the category in my quote, order into request category?

As per my understanding and the doc you uploaded there isn't really talk about request module.

Background of current system:

In the current 9.34P4 the user doesn't really use the request module directly. Quote are open only when user open a case from SRC, which used the OOB "open a request" connector to create the respective quote. 

Do like check in this case after upgrade do i need to manual re-configure the SRC catalog item with the new connector?

Regards

Soong 

 

 

Regards
Soong
0 Likes
Highlighted
Micro Focus Expert
Micro Focus Expert

Re: Upgrade steps for request module from 9.34PD to 9.51

Jump to solution

Yes, the upgrade should automatically convert those to the corresponding items in Request Fulfillment. You will also be upgrading the SRC to 9.50 so the SRC will know to interact with the new module. If you have customizations to your current Request Management module, there may be some things that need to be handled during the conflict resolution phase of the upgrade, but that is the usually the case with any module when customizations are present.

If you find that this or any other post resolves your issue, please remember to click "Accept as Solution". If you are satisfied with anyone’s response, please remember to give them KUDOS by clicking on the "thumbs up" at the bottom left of the post to show your appreciation.

View solution in original post

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.