Hello Experts,
How can i add more than one interface type (Catalog connector) to the item in the service catalog module since one of our customer wants to create multiple sequential changes when a user requests specific items.
Thank you
Regards,
Hani
Accepted Solutions


- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
You have to put the model which you wanted to make with sequantila changes to the model of change phases and tasks.
Like below:
First sequantial change= 1 task on first phase
Second sequantila change = 1 task on second phase
.......
and so on.
You can do multiple task per phase if you needed several task per change in sequence. Each task can have its own assignment group and so on.
I think it can be reproducted with one change in this way.
Vadim
HOW TO ASSIGN POINTS - Kudos - what, where, how, and why
New Forum Locations by ITRC Tree
New Forums Site Map
Want Good Answers? Ask Good Questions...


- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
Re: opening automated sequential changes for an item from SRC
hello,
You can do that either by adding multiple change tasks to the change bind to the catalog element or
- make several catalog elements
- group them in bundle
- add each category of change to each of the elements included in the bundle.
Vadim
HOW TO ASSIGN POINTS - Kudos - what, where, how, and why
New Forum Locations by ITRC Tree
New Forums Site Map
Want Good Answers? Ask Good Questions...

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
Re: opening automated sequential changes for an item from SRC
Hi Vadim,
Thank you for you reply.
OK it is clear but how can i make it sequential if i create group of items in a bundle.
Thanks
Regards,
Hani


- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
Re: opening automated sequential changes for an item from SRC
Missed that from your initial post.
In case of bundel they will be opened at the same time.
Maybe it is worth of doing based on change phase and change tasks inside of one category?
Vadim
HOW TO ASSIGN POINTS - Kudos - what, where, how, and why
New Forum Locations by ITRC Tree
New Forums Site Map
Want Good Answers? Ask Good Questions...

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
Re: opening automated sequential changes for an item from SRC
HI,
Can you tell me plz how can i configure it based on change phase.
SM v 9.31 without process designer
Thank you again
Regards
Hani


- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
You have to put the model which you wanted to make with sequantila changes to the model of change phases and tasks.
Like below:
First sequantial change= 1 task on first phase
Second sequantila change = 1 task on second phase
.......
and so on.
You can do multiple task per phase if you needed several task per change in sequence. Each task can have its own assignment group and so on.
I think it can be reproducted with one change in this way.
Vadim
HOW TO ASSIGN POINTS - Kudos - what, where, how, and why
New Forum Locations by ITRC Tree
New Forums Site Map
Want Good Answers? Ask Good Questions...

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
Re: opening automated sequential changes for an item from SRC
Hi Vadim,
Thank you so much
I've got it. so we cannot make sequential change tasks in the same phase.
your help is really appreciated
Regards,
Hani


- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Email to a Friend
- Report Inappropriate Content
Re: opening automated sequential changes for an item from SRC
Hello,
Happy to hear that.
You would really benefit if upgrade to Process Designer.
In your current built change tasks are created all at same time per phase automatically. They can be made sequantial with heavy customization which i think is not worth of it. Just separate them to different phases and avoid pain in the head.
Vadim