Project Baseline - Test asset versioning option?

[Migrated content. Thread originally posted on 21 May 2012]

Hi!

I'm about to create a baseline for the purpose of future audits, and I am uncertain what to select for the "Test asset versioning" option?

Are there any general rule of thumb here? Are there any typical uses for the two options ("Create new versions for all assets in original project" and "Create new versions for all assets in new baseline"?

Thanks in advance,

/Per
0 Likes
1 Reply

Hi,

those two option just help you to easily create a version across all manual test assets as some kind of marker for a baseline creation - otherwise you would have to do that for each manual test asset individually. So you will see in both projects (if both options have been selected) when the baseline has been created and will have a reference between the manual test assets.

Regards,
Florian
Product Owner - Silk
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.