What is the difference between 'Run Current Action' and 'Run Now' option in UFT ?

The input from the global data table is processed incorrectly when using 'Run Now' .

If 'Run Current Action' is used the logic in the script runs correctly and only the first 3 records are processed.

Which is the expected result.

This test is part of a test set in ALM.  It seems that ALM uses the same code as 'Run Now' because the input from the global data table is identical to when 'Run Now' is used in UFT.

Is there any way I can make use of 'Run Now' and only the first three records from Global Data table get processed? I want the same result using Run Now as I am getting from 'Run Current Action'.

 

Thanks,

Ankit

 

0 Likes
1 Reply
Highlighted
Respected Contributor.
Respected Contributor.

Re: What is the difference between 'Run Current Action' and 'Run Now' option in UFT ?

Hello Ankit.

For this I recommend work with a ticket, we know that you already have a ticket opened, we will continue with the investigation and as soon as possible, we will let you know an update.

Kind regards,

Susse

0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.