Hi,

We will be moving a windows server that is currently in the QA
environment to the Production environment. As it is currently in the QA
tree I want to make sure we properly remove any QA information from
edirectory on the server. After removing it from the QA tree how can we
"clean" the edirectory instance (dib files, etc) on the server before
connecting it to the Production tree?

The plan to remove the server from the QA environment is to:
- Stop eDirectory on server.
- From iManager remove any references to the server.
- "Clean" server before placing in Prod tree.

Thanks in advance!


--
IDM12
------------------------------------------------------------------------
IDM12's Profile: https://forums.netiq.com/member.php?userid=4190
View this thread: https://forums.netiq.com/showthread.php?t=51601

Labels (1)
0 Likes
2 Replies
Anonymous_User Absent Member.
Absent Member.

Re: Promoting Server from QA to Production and cleaning eDir

The only way to do this is to remove eDirectory, and NICI, entirely. With
operating systems like Linux/Unix you can just remove the DIB, or NICI
data files, and then add new stuff o the box as if it had never been in
the old tree, or you can even add a box to a tree multiple times, or into
multiple trees, but you cannot do this with the windows version.

There really is not much to clean with iManager, though when you clean out
the NICI data files (which you really should ensure is done as those are
tree-specific, and may not be deleted by the unisntall... I do not know
for sure on windows like on Linux/etc.) you may break iManager until you
reinstall everything; I do not suppose this is a big deal, but it is worth
noting.

--
Good luck.

If you find this post helpful and are logged into the web interface,
show your appreciation and click on the star below...
0 Likes
Anonymous_User Absent Member.
Absent Member.

Re: Promoting Server from QA to Production and cleaning eDir

On Tue, 26 Aug 2014 17:16:07 +0000, IDM12 wrote:

> We will be moving a windows server that is currently in the QA
> environment to the Production environment. As it is currently in the QA
> tree I want to make sure we properly remove any QA information from
> edirectory on the server. After removing it from the QA tree how can we
> "clean" the edirectory instance (dib files, etc) on the server before
> connecting it to the Production tree?


Just removing the installed software *should* be sufficient. There's an
"ndsclean.bat" in one of the Knowledgebase articles that will remove
everything, but you shouldn't need it.


--
--------------------------------------------------------------------------
David Gersic dgersic_@_niu.edu
Knowledge Partner http://forums.netiq.com

Please post questions in the forums. No support provided via email.
If you find this post helpful, please click on the star below.
0 Likes
The opinions expressed above are the personal opinions of the authors, not of Micro Focus. By using this site, you accept the Terms of Use and Rules of Participation. Certain versions of content ("Material") accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.